PRIMO PROJECT TEAM
SITE MANAGEMENT TEAM
position

project
manager

site
manager
project
administration
pre – construction -  coordinate all consultants
-  with engineering team, ensure and review that all documentations from consultants are complete   (ie. specifications. drawings, and tender documentations)
-   establish tender procedure
-   unweizing meeting
-   bid analysis.
-   negotiation with contractor
-   2nd bid analysis.
-   tender award.
-   contract document.
- coordinate all consultants
- with engineering team, ensure and review that all documentations from consultants are complete (ie. specifications. drawings, and tender documentations)
- establish tender procedure
- establish project schedule
- unweizing meeting - bid analysis.
- negotiation with contractor
- 2nd bid analysis.
- tender award.
- contract document.
- preparation of tender procedure
- contract documentation
during construction
  1. Ensure that work performed by contractors has been going according to schedule days per day.
  2. Ensure quality of work produced by contractors.
  3. Ensure the quality of materials used by contractor.
  4. Check progress submitted by contractor.
  5. Review site works satisfactory completion(ie, after rebar, after concrete works, etc)
  1. Ensure that work performed by contractors has been going according to schedule days per day.
  2. Ensure quality of work produced by contractors.
  3. Ensure the quality of materials used by contractor.
  4. Check progress submitted by contractor.
  5. Review site works satisfactory completion(ie, after rebar, after concrete works, etc)
  1. Upload daily report to website
  2. Filling of all project reports drawing
  3. All daily communication with owner, contractor and consultants
  4. Send weekly progress report to owner and consultants.
meetings a.weekly Weekly meeting with contractor - site vs drawings deviation - progress and site issues
b.monthly Monthly consultant and contractor review meeting - review of site works progress - review of schedule meeting - review for progress payment - design deviation review and confirmation Monthly planning meeting with contractor
reports a. daily     review contractor activity report
- materials used
- labour
- construction equipment
- weather
b.weekly Review all weekly report Review all weekly report review contractor progress activity report
c.monthly Review all reports Review all reports

Monthly report
- review of site works progress
- review of schedule meeting
- review for progress payment
- design deviation review and confirmation



ENGINEERING TEAM
position

architect

mep quantity
surveyor
structure
pre – construction - ensure that all architectural drawings, specifications are complete - checking the drawing architect to crosscheck with shop drawing by contractor - Checking items of work doing by contractor complied with architect drawing. - ensure that all mep drawings, and specifications are complete - checking the drawing of mep to crosscheck with shop drawing by contractor. - Checking items of work doing by contractor is in compliance with shop drawing. - Review all consultants’ bill of quantity
- Unit cost analysis.
- Calculate total project budget.
- Bid analysis
-ensure that all structure drawings, and specifications are complete.
during construction - weekly site supervision to ensure that architectural details are properly done - all specification are complied to. - weekly site supervision   - weekly site supervision
responsibility Check that architectural details are properly   - Checking the time schedule of contractor to be follow on progress.
- Checking items of works for variation order by an architect or the owner.
- Checking quality the works doing by contractor follow the contract boq of contractor.
 


During Construction :
Site management team will be responsible for day to day project performance :

  1. adherence to schedule
  2. adherence to specifications
  3. adherence to budget

Engineering team will over the site management team with monthly supervision to ensure adherence to specifications.


Pre-Construction :

  1. Engineering team (architect, mep and structure) will be responsible to review drawings and provide input to owners design.
  2. Quantity surveyor will do budget calculation, unit cost analysis and do bid analysis.
Project Administration will prepare all tender and contract documentation